Home / Description / Part / Catalogue >>                                                                                                                                                                                                                                   facebook smline-logoinstagram smyoutube sm 

ASK OUR EXPERTS

      csbyale
     
                                        

                 REQUEST A QUOTESEND AN EMAILSEE OUR LOCATION

                             

                                                                                                                                                                                                                                                               landing print  Print this Page  


                          INSTALLATION MANUAL

 

Enclosed type conductor rail[MCL] - Application
Installation Guides
1. Check the power feed box position and the installed distance of bracket
2. Bracket installation
·Bracket to be mounted should be made an oblong hole of M10 size and mounted horizontally and vertically
on the construction in order to install the sliding hanger /or fixed clamp.
3. The sliding and fixed hanger should be installed
·horizontally and vertically for PVC housing.
4. PVC housing and copper conductor installation
· Install continuously the yellow line of PVC housing, as a straight line
· After installation, the jointing cover should be installed between housing and housing.
· And then the copper conductor should be inserted in the PVC housing at the end of side.
5. Power feed box and Collector connection.
· The power feeding box should be installed at the end of any one side /or center of PVC housing with fixed clamp.
· The towing arm and collector with cable should be installed with the moving device and then the end plate
should be mounted at the end of any one side.
6. Rubber covering
·It can be installed at bottom of PVC housing.
7. Power supply
· Input power cable should be connected with power feed box.
8. operating and checking
· Please check operating. If there is no problem, you can finish installation.

 

Checking point

Finish installation
·Check installation of PVC housing horizontally and vertically as a straight line.
·Check a straight line for the yellow line of PVC housing continuously
·Check an obstruction for traveling of collector trolley
·Check correct position for power supply wiring
Check for operating
·Check the collector condition
·Check the carbon brush condition
* Note : Life time of carbon brush : approx. 5,000km
Checking and replacement for the collector
If you want to check and repair for the collector, you can change at the end of side normally.

Specially, you can remove the collector at the middle of PVC housing
as follows picture.
·Prepare 2 pcs of wood plate which width is bigger than housing width
·Insert the wood plates at the right and left side of collector
·Turn over each plate to 90 angle and then you can draw out the collector
·After replacement, it can be installed the reverse procedure
Above procedure, you should be careful for a safety.
Special applications

In case of the special application, for example, curved lines, horizontal installation, special conditions and so on, if you want to
use our enclosed-type conductor rail, we would be appreciated to get your contact.



 

 

         chester120 cm120 cmwork120 leeyoung120 pfa120   yale120simbal120 yalecm120